- Description:
-
Stichting Voorbereiding PALLAS-Reactor ("PALLAS") is pleased to invite companies to fulfil the following requirements for the Detailed Design and Construction of the Health Centre GMP Production Building in Petten (NL).
PALLAS wishes to appoint a single contractor for this work package in accordance with European tendering law. The tender consist of two stages: this Pre-Qualification stage followed by a Competitive Dialogue Procedure. The purpose of this Pre-Qualification enquiry is to identify those Applicants who are best qualified and experienced to perform the requisite work. The Health Centre is one of the PALLAS facilities that will enabling research, development, clinical trials and commercial production of radio-chemicals (start material) and radio-pharmaceuticals (medicines). The Construction of a Good Manufacturing Practice ("GMP") production building will enable the Health Centre to produce the radio-chemicals and radio-pharmaceuticals. The scope of work of the Main Contractor of the Health Centre can be described as follows: - Detailed Design of the
- Site civil works (piles, prepare area, logistical area and parking spaces)
- Architectural design
- Building core shell
- Mechanical, Electricity and Plumbing ("MEP")
- CO2/NOx emission free energy supply
- Coordination of the Bouwteam in design, construction and qualification phase. Because of the interfaces between the MEP scope and critical items out of this scope, the interface coordination must be done by the provider of the Mechanical, Electricity and Plumbing scope.
- Construction of
- Site civil works (piles, prepare area, logistical area and parking spaces)
- Building core shell
- Mechanical, Electricity and Plumbing
- CO2/NOx Emission free energy supply
- Site Acceptance Testing
- Commissioning & Qualification
- Formal hand over
- Type:
- Sealed with Preselection
- Selection phase:
- 30 Jul 2020 15:00 — 16 Mar 2022 11:00
|